The Project Team Must Take Corrective Action If Stakeholders with _____

Question 4

Multiple Choice

 The project team must take corrective action if stakeholders with _____ are categorized as resistant or unaware.


A) high interest/low power
B) high interest and high power
C) low interest/ low power
D) low interest/high power