PERT Charts Differ from the Critical Path Method in One

Question 108

Multiple Choice

PERT charts differ from the critical path method in one important way. What is it?


A) PERT charts assign one time to finish each task.
B) PERT charts are based on the use of quality principles.
C) PERT charts assign three time estimates for each activity.
D) PERT charts can be used in service organizations.

Correct Answer: