Solved

Which Scheduling Tool Shows the Necessary Sequence of Activities in a Project

Question 95

Multiple Choice

Which scheduling tool shows the necessary sequence of activities in a project and identifies the critical path?


A) Gantt chart
B) Process flowchart
C) Detailed schedule
D) Master production schedule
E) PERT chart

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions