Multiple Choice
What is the main advantage of using a PERT chart on a large scale project?
A) It aids in the ordering of supplies and materials.
B) It shows the most time-consuming path for project completion.
C) It allows managers to plan for delays.
D) It allows managers to monitor performance by comparing results with detailed schedules.
E) It identifies which tasks can be performed at the same time as others.