Solved

The Net Present Value (NPV) of a Project Is Negative

Question 60

Multiple Choice

The net present value (NPV) of a project is negative when the discount rate used is:


A) equal to the project's internal rate of return (IRR) .
B) equal to the yield to maturity of the bonds issued to finance the project.
C) greater than the project's internal rate of return (IRR) .
D) lower than the return demanded by the firm's stockholders.
E) less than the project's internal rate of return.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge