Project Risk Is Calculated by ______

Question 25

Multiple Choice

Project risk is calculated by ______.


A) historical experience with projects succeeding or not succeeding
B) the subjective judgment of the project manager
C) multiplying the likelihood of event happening with consequences of event
D) dividing the likelihood of event happening with consequences of event

Correct Answer: