Multiple Choice
"Crashing" a project ______.
A) is speeding up a project's activities to accelerate its completion
B) is equivalent to cancellation of a project
C) is the unexpected termination of a project due to an external event (e.g.,a natural disaster)
D) is the unexpected termination of a project due to an internal event (e.g.,poor management)
Correct Answer:

Verified
Correct Answer:
Verified