Multiple Choice
Generally speaking,a process is presumed to be stable and in control when ______.
A) the values on the control chart are randomly distributed around the center line
B) the values on the control chart fall outside the upper control limit
C) the values on the control chart fall outside the lower control limit
D) the values on the control chart can be traced to a special cause
Correct Answer:

Verified
Correct Answer: