Multiple Choice
Long-term capacity planning decisions such as the purchase of a new machine or construction of a new facility typically ______.
A) require significant outlays of capital
B) require government approval
C) require short lead times
D) signal a shift in strategy
Correct Answer:

Verified
Correct Answer:
Verified