The Car Service Center has the design capacity to perform an average of 60 repairs per day.The effective capacity of this repair shop is an average of 40 repairs day,while the actual repairs number an average of 36 per day.Given this information,the capacity utilization percentage is ______.
A) (36/40) * 100%
B) (36/60) * 100%
C) (40/60) * 100%
D) ((36*40) /60) * 100%
Correct Answer:

Verified
Correct Answer:
Verified
Q7: In effective global capacity management,the time horizon
Q8: Capacity-reservation contracts _.<br>A)provide the manufacturer with the
Q9: Which of the following is usually NOT
Q10: Capacity planning is LEAST likely to focus
Q11: Which of the following is FALSE with
Q13: The primary impact of poorly developed global
Q14: Which of the following is NOT one
Q15: Design capacity is _.<br>A)the maximum rate of
Q16: Which of the following is NOT a
Q17: The purpose of capacity control is _.<br>A)to