Multiple Choice
Long-term capacity planning decisions such as the purchase of a new machine or construction of a new facility typically ______.
A) call for significant outlays of capital
B) require approval from the supervisor of each shift
C) need to be cleared by the government
D) can be decided only by the board of directors
Correct Answer:

Verified
Correct Answer: