Multiple Choice
Using multiple suppliers and suppliers that have flexibility in capacity to respond to demand changes is a mitigation strategy for ______.
A) capacity risk
B) demand risk
C) performance risk
D) strategy risk
Correct Answer:

Verified
Correct Answer:
Verified