If the average daily demand rate is 50 units per day and the lead time is 3 days,then the reorder point is ______.
A) 50 / 3 (i.e.,about 17 units)
B) 50 * 3 (i.e.,150 units)
C) 50 ^ 3 (i.e.,125,000 units)
D) 50 units