Multiple Choice
Net requirements is calculated as ______.
A) Gross requirements + on-hand inventory
B) Gross requirements - on-hand inventory
C) Gross requirements x on-hand inventory
D) Gross requirements ÷ on-hand inventory
Correct Answer:

Verified
Correct Answer:
Verified
Q41: In part-period balancing lot-sizing technique,_.<br>A)the order interval
Q42: Disaggregation refers to breaking down end-product requirements
Q43: The time at which materials that have
Q44: Which of the following is NOT a
Q45: A JIT system schedules _.<br>A)parts<br>B)capacity<br>C)MPS<br>D)operations
Q47: The focus of the master schedule in
Q48: Which of the following is NOT an
Q49: The planning horizons of master scheduling are
Q50: An approach to reducing the effect of
Q51: The difference in time between planned order