Multiple Choice
The process of dividing the master scheduling planning horizon to allow for different rules for making changes is called ______.
A) MPS splitting
B) MPS dividing
C) time fencing
D) planning horizon division
Correct Answer:

Verified
Correct Answer:
Verified