Multiple Choice
The focus of the master schedule in an MTS production environment is ______.
A) to produce finished goods to meet inventory and customer service levels
B) to produce components ready to be assembled upon receipt of customer order
C) to ensure that raw materials are readily available to being production upon receipt of order
D) to continuously produce finished goods irrespective of inventory level
Correct Answer:

Verified