The difference between scheduled receipts and planned order receipts is that ______.
A) no difference
B) planned order receipts are for orders already placed,scheduled receipts show quantity that is expected to be received
C) scheduled receipts are for orders already placed,planned order receipts show quantity that is expected to be received
D) planned order receipts authorize scheduled receipts
Correct Answer:

Verified
Correct Answer:
Verified
Q55: What is the process that identifies which
Q56: The lot-sizing technique which almost eliminates inventory-holding
Q57: In fixed-period ordering technique,_.<br>A)the order interval is
Q58: Checking for available capacity at the materials
Q59: The time when raw materials,components,or subassemblies are
Q61: Information about supplier,lead time,and lot-size policy is
Q62: A benefit of MRP is the _.<br>A)reduction
Q63: Which capability of an MRP system helps
Q64: Frequent changes to an MRP system cause
Q65: Master scheduling deals with products at what