Multiple Choice
With regard to capacity planning,the difference between an integrated MRP-JIT system and an only-MRP system is that ______.
A) the MRP system uses finite capacity planning; the integrated MRP-JIT system uses infinite capacity planning
B) the MRP system uses infinite capacity planning; the integrated MRP-JIT system uses finite capacity planning
C) there is no difference; both systems use finite capacity planning
D) there is no difference; both systems use infinite capacity planning
Correct Answer:

Verified
Correct Answer:
Verified
Q13: Sufficiency of capacity for the output of
Q14: Materials requirements planning deals with products at
Q15: An exception report is a _ of
Q16: Updating or replanning the MRP records is
Q17: In order for MRP implementation to be
Q19: In lot-for-lot lot sizing,_.<br>A)inventory holding costs are
Q20: The changes in firm planned orders _.<br>A)happen
Q21: A planned order release is a _
Q22: Which of the following reports can be
Q23: MRP outputs reports are available to _.<br>A)production