Multiple Choice
______ charts show the loads on various work centers,equipment,or facilities as well as the associated idle times.
A) Gantt load
B) Gantt schedule
C) Gantt sequence
D) Gantt output
Correct Answer:

Verified
Correct Answer:
Verified