The average tardiness for the job listed in the table below under the longest processing time (LPT) rule is ______.  Job  Processing time  {in days}  Due date {in days from  today’s date}  A 49 B 1018 C 66 D 1219 E 717\begin{array} { | c | c | c | } \hline \text { Job } & \begin{array} { c } \text { Processing time } \\\text { \{in days\} }\end{array} & \begin{array} { c } \text { Due date \{in days from } \\\text { today's date\} }\end{array} \\\hline \text { A } & 4 & 9 \\\hline \text { B } & 10 & 18 \\\hline \text { C } & 6 & 6 \\\hline \text { D } & 12 & 19 \\\hline \text { E } & 7 & 17 \\\hline\end{array}


A) 16 days
B) 14 days
C) 15 days
D) 13 days