Multiple Choice
Purple Airlines has ordered 30 small jets from its supplier.The supplier has estimated the first aircraft will require 350 days of direct labor to manufacture and assemble.Based on past experience,the supplier estimates the learning curve to be 75%.Estimate the number of days of direct labor for the 15th jet aircraft.
A) 113.75 days
B) 115.32 days
C) 120.43 days
D) 116.87 days
Correct Answer:

Verified
Correct Answer:
Verified