Question 76

Multiple Choice

A construction firm wants to estimate the direct labor of a worker who will perform multiple iterations of tasks.The worker must do a total of 20 of these activities to reach steady state.The time estimated to perform the 20th iteration is 2 hours,and the learning rate for this repetitive activity is 70%.The cost of labor is $40/hr.Estimate the direct labor cost for 20 iterations of these activities.


A) $2,767.25
B) $2,341.45
C) $3,456.65
D) $1,234.12