Multiple Choice
Acme,Inc.,produces widgets.To manufacture a new type of widget,it took 50 hours for the first widget.Acme estimates it has a 97% learning rate.Using the logarithmic approach,calculate the time it will take to manufacture the 56th widget.
A) 31.05 hours
B) 41.90 hours
C) 18.96 hours
D) 42.87 hours
Correct Answer:

Verified
Correct Answer:
Verified