Multiple Choice
Acme,Inc.,produces widgets.To manufacture a new type of widget,it took 100 hours for the first widget.Acme estimates it has a 95% learning rate.Using the logarithmic approach,calculate the time it will take to manufacture the 75th widget.
A) 62.89 hours
B) 72.70 hours
C) 56.55 hours
D) 76.42 hours