Multiple Choice
Weston,Inc.,produces widgets.To manufacture a new type of widget,it took 22 iterations before the process reached a steady state of 10 hours.If Weston has a 96% learning rate,use the logarithmic approach to calculate the time it took to manufacture the first widget.
A) 12.00 hours
B) 13.80 hours
C) 11.71 hours
D) 9.81 hours
Correct Answer:

Verified
Correct Answer:
Verified