Multiple Choice
Weston,Inc.,produces widgets.To manufacture a new type of widget,it took 15 iterations before the process reached a steady state of 13 hours.If Weston has an 81% learning rate,use the logarithmic approach to calculate the time it took to manufacture the first widget.
A) 29.61 hours
B) 30.14 hours
C) 29.47 hours
D) 28.44 hours
Correct Answer:

Verified
Correct Answer:
Verified