Multiple Choice
The relationship between two or more tasks that requires certain tasks to be done before others is known as ______.
A) a precedence relationship
B) a Muther's grid relationship
C) points of indifference
D) an assembly relationship
Correct Answer:

Verified
Correct Answer:
Verified