    The Daily Output Required from an Assembly Line Is 120
Solved

The Daily Output Required from an Assembly Line Is 120

Question 70

Question 70

Multiple Choice

The daily output required from an assembly line is 120 units.If the line operates 8 hours a day,what is the cycle time per unit?


A) 4 hours
B) 4 minutes
C) 15 seconds
D) 1 hour

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q65: As real-life layout problems are typically large,arriving

Q66: ALDEP is _.<br>A)used to balance asymmetric production

Q67: Idle time is computed by using which

Q68: The time required for the line to

Q69: CORELAP is _.<br>A)used to balance asymmetric production

Q71: An assembly line to be balanced

Q72: Which of following can be used to

Q73: In process layouts,the process facilities are shared

Q74: _ is the time required for the

Q75: The time required to completely produce an

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines