In the Context of a CRP System,a Load Represents ______

Question 2

Multiple Choice

In the context of a CRP system,a load represents ______.


A) the setup time plus run time required from a specific work center
B) the product of the setup time and the run time required from a specific work center
C) the ratio of the setup time to the run time required from a specific work center
D) the difference between the setup time and the run time required from a specific work center

Correct Answer: