Developing MRP Plans and Schedules by Assuming Infinite Capacity and On-Time,correct

Question 98

Multiple Choice

Developing MRP plans and schedules by assuming infinite capacity and on-time,correct delivery of materials ordered by the suppliers is known as ______.


A) assumption-based manufacture
B) open loop MRP system
C) CRP II
D) batch manufacture

Correct Answer: