Multiple Choice
Developing MRP plans and schedules by assuming infinite capacity and on-time,correct delivery of materials ordered by the suppliers is known as ______.
A) assumption-based manufacture
B) open loop MRP system
C) CRP II
D) batch manufacture
Correct Answer:

Verified
Correct Answer:
Verified