Multiple Choice
Larry has booked a hotel room for a conference at a rate of $100 per day for five days.When he arrives to check in,Larry is told that the hotel was overbooked and it cannot supply him with a room.Larry is forced to go to the only hotel in town with available rooms and pay $150 per night.If Larry sues the original hotel for damages and wins
A) he will be entitled to compensatory damages in the amount of $250.
B) he will be entitled to consequential damages in the amount of $250.
C) he will not be entitled to any damages because the additional costs were not foreseeable.
D) he will be entitled to liquidated damages in the amount of $250.
Correct Answer:

Verified
Correct Answer:
Verified
Q2: In some states,another name for a "statute
Q3: What is an anticipatory repudiation,and what must
Q4: Substantial performance will be enforced only if
Q5: Damages agreed to by the parties when
Q6: Nominal damages are rarely awarded in contract
Q8: Sally has just purchased a home and
Q9: Mel is under contract with a textbook
Q10: Toby is a licensed plumber and has
Q11: Fred's Flooring (FF)contracted with Harry homeowner to
Q12: Impossibility of performance is subjective,meaning that one