Multiple Choice
In Hadley v.Baxendale,when Hadley sued because Baxendale took unnecessary time to get a crankshaft repaired,causing Hadley's mill to close for an extended time,the court found
A) Baxendale owed Hadley compensatory damages because the mill was shut down for an extended time directly as a result of Baxendale's delayed delivery.
B) Baxendale owed Hadley consequential damages because the mill was shut down for an extended time as a result of Baxendale's delayed delivery and the shutdown was a foreseeable indirect result of Baxendale's delay.
C) Baxendale did not owe Hadley consequential damages because the extended closing time was not foreseeable despite Baxendale's delay in delivery.
D) Baxendale did not owe Hadley either compensatory or consequential damages but did owe punitive damages due to the unreasonable delay in delivery.
Correct Answer:

Verified
Correct Answer:
Verified
Q45: Patios R Us contracts with Karl's Concrete
Q46: Assignments require the consent and agreement of
Q47: How does an assignment differ from a
Q48: When a party breaches a contract,the non-breaching
Q49: Lon has just come home from serving
Q51: A rescission of a contract may occur
Q52: Moe has entered into a contract with
Q53: Amos owns a piece of land along
Q54: In what way do legal remedies and
Q55: Which of the following is not an