In the WBS Approach,the Project Plan Is First Broken Down

Question 9

Multiple Choice

In the WBS approach,the project plan is first broken down into tasks placed on the WBS task list.The minimum attributes that should be identified for each task include all but which of the following?


A) Work to be accomplished (activities and deliverables)
B) Estimated amount of effort required for completion, in hours or workdays
C) The common or specialized skills needed to perform the task
D) Task independencies