It is possible to take a very complex operation and diagram it in PERT if you can answer three key questions about each activity.Which of the following is NOT one of them?
A) How long will it take?
B) What activity occurs immediately before this activity?
C) What activity occurs immediate activity after this activity?
D) What other activities require the same resources as this activity?
Correct Answer:

Verified
Correct Answer:
Verified