Multiple Choice
In the NIST performance measures implementation process,the comparison of observed measurements with target values is known as a ____ analysis.
A) shortfall
B) gap
C) corrective
D) failure
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q7: Which of the following is the last
Q8: Information security _ is the process of
Q9: Problems with benchmarking include all but which
Q10: The second step in the NIST SP
Q11: One of the three goals of System
Q13: In reporting InfoSec performance measures,the CISO must
Q14: Security Certification & Accreditation initiative offers several
Q15: When an organization applies statistical and quantitative
Q16: Designing the performance measures collection process requires
Q17: One of the priorities in building an