Multiple Choice
When applied to project management,the resource management knowledge area typically involves which of the following processes?
A) ensuring the project includes all the work required, and only the work required, to complete the project successfully
B) planning, estimating, budgeting, financing, funding, managing and controlling costs
C) conducting risk management planning, identification, analysis, response planning & implementation, and monitoring
D) identifying, acquiring, and managing resources needed to successfully complete the project
Correct Answer:

Verified
Correct Answer:
Verified
Q7: The name and number of phases in
Q8: Project customers can be either internal or
Q9: In reality,many projects are fully successful in
Q10: All projects go through a common project
Q11: Which of the following actions will likely
Q13: Once projects are completed,they will typically yield
Q14: Which of the following examples is<u> NOT</u>
Q15: Compare and contrast predictive,or plan-driven project life
Q16: Project failure can result from all of
Q17: Which of the following statements correctly describes