Multiple Choice
Achieving project success is determined by all of the following EXCEPT:
A) creating deliverables that include all required features
B) involving only important key stakeholders
C) completing the project on schedule and on budget
D) providing outputs that please the project's customers
Correct Answer:

Verified
Correct Answer:
Verified