Multiple Choice
The addition of acceptance criteria factors to the milestone schedule in a project charter helps the team understand who will judge the quality of the deliverable associated with each milestone,and _____.
A) that stakeholder's role on the team.
B) the risk associated with each milestone.
C) the penalties for not achieving the desired quality.
D) what criteria will be used for that determination.
Correct Answer:

Verified
Correct Answer:
Verified