Multiple Choice
The project life cycle where project teams plan in short bursts (generally of one to four weeks) ,often called sprints or iterations,is referred to as _________:
A) Construction project life cycle
B) Predictive, plan-driven project life cycle
C) Adaptive, change-driven project life cycle
D) Process improvement life cycle