In Agile Projects,overall Planning Is at a High Level,and Only

Question 48

Multiple Choice

In agile projects,overall planning is at a high level,and only the near-term work is planned in detail.The project work is conducted in iterations (sprints) that are normally: 


A)  no more than one calendar year 
B)  a variable length depending on project scope 
C)  a fixed length of two or four weeks 
D)  assigned to one person on the team

Correct Answer: