Multiple Choice
Which of these is NOT one of the primary types of information captured in a project meeting?
A) action items agreed to.
B) evaluation of the meeting.
C) resolved issues and new issues.
D) assumptions and constraints.
Correct Answer:

Verified
Correct Answer:
Verified