    When a Project Team Needs to Construct a WBS,it Needs
Solved

When a Project Team Needs to Construct a WBS,it Needs

Question 18

Question 18

True/False

When a project team needs to construct a WBS,it needs to include in its planning team a subject matter expert (SME)who understands how each segment of the work will be accomplished.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q13: Baselining is defined as a method of

Q14: All of the following elements should be

Q15: On agile projects,the scope definition begins with

Q16: All of the following statements correctly describe

Q17: The project scope is the work that

Q19: The priority of the product in agile

Q20: While many projects may have a primary

Q21: It is important to assign a unique

Q22: Organizing the second level of the Work

Q23: Failure to include project management in the

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines