Multiple Choice
Which of the following items best describes a project Work Breakdown Structure (WBS) ?
A) an organizational chart depicting who will perform project work
B) a schedule depicting when project work will be performed
C) a tool that the team uses to progressively divide deliverables into smaller and smaller pieces
D) a list of activities to complete the project work packages
Correct Answer:

Verified
Correct Answer: