Multiple Choice
Work Breakdown Structures typically include one or more intermediate levels.Which of the following statements correctly describe the nature of these intermediate levels?
A) They generally represent items that need to be created in order to produce the final deliverables.
B) They generally represent the raw materials required to create the final deliverables.
C) They generally represent the resource assignments to create the final deliverables.
D) They generally represent the sequence and timing of work packages
Correct Answer:

Verified
Correct Answer:
Verified
Q5: What are some of the benefits of
Q6: The Work Breakdown Structure (WBS)is a framework
Q7: A WBS dictionary is a document that
Q8: The overall project is considered to be
Q9: Explain how scope is defined on agile
Q11: The project scope refers to the features
Q12: Since work packages provide the basis for
Q13: Baselining is defined as a method of
Q14: All of the following elements should be
Q15: On agile projects,the scope definition begins with