Multiple Choice
This term is defined as the total number of work periods (not including holidays or other non-work periods) required to complete a schedule activity,usually expressed as workdays or workweeks:
A) effort
B) elapsed time
C) duration
D) resource days
Correct Answer:

Verified
Correct Answer:
Verified