Multiple Choice
Despite the insights that PERT provides,there are still practical limitations that impact its usefulness.All of the following difficulties are associated with the use of PERT EXCEPT:
A) It often requires more effort to generate three estimates than one.
B) It highlights uncertainty in project duration
C) It does not accurately address the case when two activities both need to be accomplished before a third can begin.
D) There is no assurance that three estimates are any more accurate than one
Correct Answer:

Verified
Correct Answer:
Verified
Q20: Many factors can impact the accuracy of
Q21: In order for activities to be useful
Q22: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-2 Research
Q23: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-4 Lab
Q24: Which of these represents a typical problem that
Q26: To use the enumeration method of determining
Q27: The primary advantage of PERT is that
Q28: If the project manager changes an activity
Q29: The critical path is the sequence of
Q30: Except in rare circumstances,project teams should not