Multiple Choice
A common tool project teams use is a responsibility assignment matrix (RAM) .Typically,this chart will depict:
A) the early start and early finish, and late start and late finish, of each schedule activity.
B) the duration of each activity.
C) all the work packages and the resources assigned for various responsibilities regarding each work package.
D) the hierarchical organizational reporting structure.
Correct Answer:

Verified
Correct Answer:
Verified
Q32: Project managers find many advantages in having
Q33: An example of fast tracking a project
Q34: What should a project manager's considerations be
Q35: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 8-2 Software
Q36: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 8-3 Programmers
Q38: Estimate Activity Resources focuses exclusively upon the
Q39: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 8-4 Project
Q40: Crashing is a project schedule compression technique
Q41: When constructing a responsibility matrix or "RACI"
Q42: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 8-4 Project