On Agile Projects,detailed Risk Management Activities May Occur During All

Question 10

Multiple Choice

On agile projects,detailed risk management activities may occur during all of the following times EXCEPT: 


A)  While planning each subsequent iteration. 
B)  During early risk planning at the start of the project. 
C)  In daily stand-up meetings. 
D)  During retrospectives at the end of each iteration.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge