Multiple Choice
Which of the following describes how the team uses a cause-and-effect diagram to support project risk analysis?
A) The project team begins by identifying strengths, weaknesses, opportunities and threats.
B) The team organizes assumptions and constraints in a fishbone pattern.
C) The team lists the risk as the "effect" in a box at the head of a fish, then names the big bones.
D) Team members are encouraged to keep asking "when?" to break down risks into more detailed causes.
Correct Answer:

Verified
Correct Answer:
Verified
Q26: Which of the following activities illustrates a
Q27: When complete,the risk register presents the results
Q28: Once risks have been identified and analyzed,the
Q29: In Agile projects early risk planning,assessment and
Q30: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 10-1 Excerpt
Q32: The purpose of risk management is to
Q33: All of the following activities illustrate a
Q34: The cost per risk for risks discovered
Q35: How might you approach the prioritization of
Q36: Perform Quantitative Risk Analysis is the process