Multiple Choice
Under normal conditions,which of these contract types poses the greatest risk to the buyer?
A) Firm-Fixed-Price (FFP)
B) Fixed-Price-Incentive-Firm (FPIF)
C) Cost-Plus-Fixed-Fee (CPFF)
D) Time and Material (T&M)
Correct Answer:

Verified
Correct Answer:
Verified